25-landfill-recycle-center

$1,964,775.00
In stock
SKU
2054
Landfill Recycle Center: mixed landfill items ride the belt past the seven stages, each kind drops into its own bale, and the rest goes to thermal processing that makes electricity, animated picture

Asset valuation: $2,400,000,000. Stationary Landfill Mining and Resource Recovery Facility - Price: $50,000,000 - Status: Complete Engineering Package - Author: Christopher Gabriel Brown - Date: March 2026 - Patent Portfolio: Consolidated utility application 19/540,453 (filed 02/13/2026)

Think of a closed landfill the way a miner thinks of an old hillside: everything ever thrown in is still there, and most of it is worth more sorted than buried. The Landfill Recycle Center is the fixed-site plant that does the sorting. It takes one thousand tons of excavated landfill a day through seven stages of equipment already on the market - trommel screens, magnets, eddy-current separators, density splits, near-infrared optical sorters, a manual quality-control line with balers, and a thermal unit that turns what cannot be recycled into electricity. Out the other side come baled metals, plastics sorted by resin, glass cullet and aggregate, recovered soil, and more electricity than the plant uses.

This is the permanent cousin of the mobile-truck idea: a concrete pad instead of a weight limit, one facility permit instead of a permit per stop, and ten to fifty times the throughput. It puts up to 65.4 percent of the input back into commerce, keeps eighty-five to ninety-five percent of it out of the ground, and runs with a crew of fourteen in autonomous mode.

It is for landfill owners, waste-to-energy operators and the engineering buyers who build for them. What ships is a ready-to-permit package: every formula worked through, dimensional drawings, a bill of materials of more than eighty line items from named manufacturers, the energy-recovery thermodynamics, a three-scenario business plan, a federal, state and local permitting guide, and a working Python control-system simulator. The design is patent pending, and the inventor keeps the rights to seek further protection.

Description

Project 25 — Landfill Recycle Center
Inventor: Christopher Gabriel Brown

Patent status: Consolidated utility application 19/540,453 (filed 02/13/2026). Patent pending; all rights to seek additional patent protection are expressly reserved by the inventor.

SKU: 2054
Document revision: 1.0 — March 2026
Maturity level: 1 — Research (Complete Engineering Package)
Overview

A fixed-site industrial facility that mines closed or active landfills, separates materials into saleable commodities, recovers energy from non-recyclables, and produces clean water. Unlike a mobile-truck concept (Project 15), this is a permanent processing center with full-scale industrial equipment, no weight constraints, and 10–50× the throughput. The design basis is 1,000 tons per day of excavated municipal landfill feedstock, processed through a seven-stage pipeline of commercially proven equipment — trommel screening, magnetic separation, eddy-current separation, density separation, NIR optical sorting, manual QC, and thermal waste-to-energy — producing baled metals, sorted plastics by resin, recovered soil and aggregate, and net-positive electricity.

The package delivers a complete, ready-to-permit engineering blueprint: technical specifications with every formula worked through, facility layout with dimensional drawings, a full bill of materials quoting 80+ line items from named manufacturers, an energy-recovery thermodynamic analysis, a business plan with three-scenario sensitivity modelling, a regulatory-compliance and permitting guide covering federal, state and local requirements, an autonomous-operations architecture targeting 90%+ unmanned running, and a working Python SCADA / control-system simulator.

Facility vs. Truck — Why a Stationary Center
Constraint Mobile Truck (Project 15) Stationary Center (Project 25)
Processing capacity 10–50 tons/day 500–2,000 tons/day
Equipment weight limit ~30 tons total Unlimited (concrete pad)
Power generation 100 kW max onboard 1–5 MW grid-tied
Separation stages 3 (cramped) 7 (full industrial)
Maintenance access Field service only Full shop on-site
Permitting Each site needs permits One facility permit
Uptime 60–70% (travel, setup) 85–95% (industrial standard)
Material storage 16–26 containers on truck Unlimited yard storage
Water/energy recovery Token amounts Full industrial scale
Facility Specifications
Parameter Value

Minimum site area 25.0 acres (processing hall 3.5 ac, feedstock staging 4.0 ac, recovered-materials storage 2.5 ac, thermal unit 1.5 ac, water treatment 1.5 ac, internal roads 3.0 ac, admin/parking 1.5 ac, buffer/setback 7.5 ac)

Processing hall 200 ft × 600 ft clear-span — 120,000 ft² (2.75 acres), 60 ft eave height, pre-engineered metal building

Thermal processing building 150 ft × 100 ft — 15,000 ft², 8‑inch CMU walls to 12 ft, insulated metal panel above

Administration building 60 ft × 80 ft — 4,800 ft² (offices, QC lab, break room, locker rooms, IT/server room)

Maintenance shop 60 ft × 80 ft — 4,800 ft² (two drive-through bays, welding area, parts storage)

Design-basis input 1,000 TPD = 50 TPH (20-hour operating day)
Operating schedule 16 hours/day, 6 days/week (2 shifts), 260–330 days/year
Workforce 33–35 per shift (conventional), or 14 total (autonomous mode)

Electrical service 12 MW capacity, redundant feeders, 13.8 kV primary stepped to 4,160 V and 480 V

Fire water 8‑inch main, 1,500 GPM at 125 psi, 300,000‑gallon storage tank
Overhead crane 20‑ton main hoist, 5‑ton auxiliary, 195 ft span, CMAA Class D
Ventilation 720,000 CFM (24 × 30,000 CFM roof-mounted supply fans), 6 ACH minimum
Material recovery rate 57.4% direct material + 8.0% ash-reuse potential = up to 65.4%
Landfill diversion rate 85–95%
Net electricity export 2.3–9.9 MW depending on configuration
Seven-Stage Processing Pipeline
Stage Technology Key Equipment Throughput Power Draw

1. Receiving & Trommel Screening Rotating drum screens, three-zone (25 mm / 150 mm apertures) Doppstadt SM 720.2 (2 units), Lindner Urraco 75DK shredder, McCloskey R230 scalping screen 120–160 TPH combined 355–445 kW

2. Magnetic Separation Overhead suspended electromagnet + drum magnet (two-stage) Eriez SE‑7 / CP‑30 suspended magnet, Eriez RE7 / Steinert UME drum magnet, Eriez Xtreme head pulleys 60–80 TPH 31–35 kW

3. Eddy Current Separation Eccentric-pole rotor at 3,000+ RPM Steinert EddyC FINES (2 units), Bunting eFines ECS, Eriez RevX‑E 40–60 TPH 52–53 kW

4. Density Separation Zig-zag air classifier + sink-float tank Westeria Windshifter ADS‑2000 (2 units), BRT Hartner Autosort 6F ballistic separator, Outotec HMS drum 40–60 TPH (air) / 15–25 TPH (sink-float) 156–211 kW

5. Optical / NIR Sorting Near-infrared spectroscopy + visible camera + AI robotics TOMRA AUTOSORT 5 (2 units), Steinert KSS XT FLI (XRF), Binder+Co CLARITY (glass), ZenRobotics ZRR2 (2 units, 80 picks/min per arm) 4–10 TPH per unit 157–217 kW

6. Manual QC & Baling Elevated picking line (8–10 stations) + horizontal auto-tie balers Machinex MACH Sort conveyor, Bollegraaf HBC‑120S baler (120‑tonne ram), Sierra International RB6000 two-ram baler, CP Manufacturing can densifier 5–10 TPH (picking), 8–12 bales/hour 90–108 kW

7. Thermal Processing (WtE) Moving-grate stoker or fluidized-bed combustion + HRSG + condensing steam turbine Valmet BFB boiler (30 MW th ), Siemens SST‑200 turbine-generator (8 MW e ), Babcock & Wilcox SPCC + baghouse FGT, Yara/Johnson Matthey SCR 8–17 TPH (grate) / 5–12 TPH (gasifier) 395–565 kW (parasitic)

Aggregate power: Total facility consumption 1,236–1,634 kW. Gross thermal generation 1,000–2,000 kW (processing-stages document) to 13.8 MW (tech-specs large-scale scenario). Net facility power position ranges from −634 kW to +764 kW at processing-stage scale, or up to 9.9 MW net export in the large-scale configuration.

Mass Balance — 1,000 TPD Design Basis

Material % of Input TPD TPH
Paper & cardboard 25% 250 12.5
Food & yard waste (degraded) 15% 150 7.5
Plastics (all types) 13% 130 6.5
Metals (ferrous + non-ferrous) 9% 90 4.5
Glass 6% 60 3.0
Other / inerts (soil, C&D, textiles) 32% 320 16.0
Total 100% 1,000 50.0
Recovery Summary
Product TPD % of Input Disposition
Ferrous metals 57 5.7% Baled, sold to scrap dealers
Non-ferrous metals 13.2 1.3% Sorted (Al/Cu/brass), sold
PET plastic 24 2.4% Baled, sold to reclaimers
HDPE plastic 30 3.0% Baled, sold to reclaimers
PP plastic 16 1.6% Baled, sold to reclaimers
Glass cullet / aggregate 284 28.4% Aggregate, daily cover, glass recycler
Soil / fine inerts 120 12.0% Beneficial reuse (ADC, fill)
QC-recovered material 30 3.0% Various commodity streams
Electricity (net export) — — 2.3–9.9 MW net to grid
Total diverted from landfill 574.2 57.4%
Bottom ash (potential reuse) 80 8.0% Aggregate if TCLP-passing
Fly ash (disposal) 14 1.4% Stabilised, monofill
Flue gas (atmospheric) 262 26.2% CO 2 + H 2 O primarily
Process losses / moisture 70 7.0% Evaporation, mechanical loss
Energy Recovery & Thermodynamics
Parameter Value
Weighted lower heating value (dry) 16.10 MJ/kg
Effective LHV (25% moisture) ~12 MJ/kg (formula: LHV eff = LHV dry × (1 − m) − m × h fg )
Thermal input at 300 TPD 41.67 MW th

Boiler efficiency 82% (natural-circulation water-tube, 3-pass, ~1,200 m² heat-transfer area)

Steam conditions 40 bar / 400 °C superheated, 44.3 tonnes/hour
Steam enthalpy 3,214 kJ/kg (from steam tables)
Turbine isentropic efficiency 78%
Generator efficiency 96%
Mechanical efficiency 98%
Rankine-cycle thermal efficiency 29.6%
Design gross electrical output 3.0 MW e (peak 3.5 MW)

Parasitic loads 0.7 MW (combustion-air fans 250 kW, FGT fans 120 kW, boiler-feed pumps 80 kW, condensate pumps 30 kW, cooling-tower fans 60 kW, ash handling 50 kW, SCADA/controls/lighting 40 kW, SCR reagent 30 kW, baghouse cleaning 40 kW)

Net export 2.3 MW
Net electrical efficiency 5.5%
Net plant heat rate 18.1 MJ/kWh (17,160 BTU/kWh)
Annual net export 11,536–17,250 MWh/year
Annual electricity revenue $692,160–$1,725,000

Facility energy ratio 2.05× (energy-positive — generates approximately twice the energy consumed)

CHP potential: Combined heat and power configuration could capture 20–30 MW thermal for process-water heating, building HVAC, or adjacent industrial users, raising overall efficiency to ~41.5%.

Equipment Bill of Materials — 80+ Line Items, 12 Categories
Category Line Items Subtotal (USD)

1. Screening Equipment 5 items (Doppstadt SM 720.2 ×2, Metso CVB 2060 ×2, BIVITEC 300, McCloskey R230, BRT Hartner Star Screen) $1,980,000

2. Separation Systems 12 items — magnetic (Eriez CP‑30 ×2, Steinert UME ×2, Eriez head pulleys ×4), eddy-current (Steinert EddyC ×2, Bunting eFines), density (Westeria ADS‑2000 ×2, BRT Hartner Autosort 6F, Outotec HMS), optical/sensor (TOMRA AUTOSORT 5 ×2, Steinert KSS XT FLI, Binder+Co CLARITY, ZenRobotics ZRR2 ×2) $4,502,000

3. Conveyor Systems 7 types, 39 units total (Continental primary ×2, Fenner Dunlop transfer ×12, Martin chevron ×4, Machinex MACH Sort ×2, Superior TeleStacker ×3, Hapman drag-chain ×2, Martin belt cleaners ×14) $2,094,000

4. Thermal / Waste-to-Energy 7 items (Valmet BFB boiler, Siemens SST‑200 turbine, B&W SPCC + baghouse, Yara SCR, ABB/Sick CEMS, Magaldi ash conveyor, Vecoplan VEZ 3200 RDF shredder) $12,655,000

5. Material Handling 7 items (CAT 966M ×2, CAT 336 GC, JCB 940‑4 ×2, Toyota 8FBN30 ×3, Konecranes CXT crane, CAT G320D grapple ×2, Bobcat S770 ×2) $1,907,000

6. Baling & Compaction 5 items (Bollegraaf HBC‑120S, Sierra RB6000 two-ram, CP can densifier, Tama Lastic bale wrapper, Bollegraaf bale conveyor) $1,315,000

7. Water Treatment 7 items (Highland Tank leachate EQ, Pall Aria MBR, Dow FilmTec RO, GSE HDPE liner, Highland OWS‑100, Grundfos chemical dosing, Andritz screw press) $1,762,000

8. Controls & SCADA 7 items (Siemens WinCC V8.0 redundant SCADA, Siemens S7‑1500 PLCs ×8, ABB MNS iS MCCs ×3, ABB ACS580 VFDs ×30, Axis P3265 cameras ×24, Cisco IE‑4010 switches ×6, Siemens SITRANS belt scales ×6) $1,570,200

9. Safety & Fire Protection 7 items (Honeywell NFS2‑3030 fire alarm, Viking VK500 sprinkler, Chemguard AFFF, GreCon spark detection ×8, Haws 8300 shower stations ×6, Draeger Polytron 7000 gas detection ×10, Pilz PSENmlock safety system) $869,200

10. Weigh Bridges 4 items (Mettler Toledo VTC221 truck scales ×2, ScaleMate software ×2, MobyDick wheel wash) $456,000

11. Dust Control 5 items (Donaldson Torit DLM baghouse ×2, BossTek DB‑60 ×4, Nordfab ducting, BossTek Fusion mobile, Thermo Fisher TEOM stations ×3) $892,000

12. Buildings & Structures 9 items (Nucor processing hall 3,200 m², Nucor WTE building 750 m², Butler admin 600 m², Machinex sorting cabins ×2, ClearSpan storage bays ×4, Justrite chemical storage, Butler workshop, ModSpace gatehouse, civil works) $6,840,000

Summary Amount (USD)
Equipment subtotal $36,842,400
Engineering & design (8%) $2,947,400
Installation & commissioning (12%) $4,421,100
Freight & logistics (3%) $1,105,300
Contingency (10%) $3,684,200
Spare-parts inventory (2%) $736,800
Total installed project cost $49,737,200
Emissions Control & Regulatory Compliance
Pollutant EPA MACT Limit (40 CFR 60 Subpart Eb) Design Outlet Safety Margin
Particulate matter 20 mg/dscm 4×
CO 100 ppmv 2×
NO x 150 ppmv 2×
SO 2 29 ppmv 2×
HCl 25 ppmv 3×
Dioxins / furans 30 ng/dscm 60×
Mercury 50 μg/dscm 5×

All values corrected to 7% O 2 , dry basis, standard conditions (0 °C, 1 atm). APCD train: furnace → HRSG → spray-dryer absorber (hydrated lime) → activated-carbon injection → pulse-jet baghouse (PTFE membrane bags, ~2,000 bags, 2,000 m² filtration area) → SCR reactor (V 2 O 5 ‑WO 3 /TiO 2 honeycomb, >80% NO x reduction) → ID fan → 200 ft stack (6 ft inside diameter). CEMS monitors CO, NO x , SO 2 , HCl, O 2 , PM, Hg, temperature, and flow continuously, with data logged per EPA 40 CFR Part 60.

Regulatory framework covered in full: RCRA (40 CFR Parts 239–282), Clean Air Act Title V, NSPS Subpart Eb, MACT Subpart EEE, NPDES (40 CFR Part 122), pretreatment (40 CFR Part 403), NEPA (40 CFR Parts 1500–1508), OSHA (29 CFR Part 1910 — 14 specific standards addressed including HAZWOPER, LOTO, confined-space, noise exposure, machine guarding, hazard communication), 10 safety programs documented, permitting timeline 18–36 months, permitting costs $542,000–$1,070,000, annual compliance $335,000–$515,000.

Revenue Model & Financial Analysis
Revenue Stream Low Estimate (annual) High Estimate (annual)
Ferrous metals (steel, iron) $2,527,200 $3,510,000
Non-ferrous metals (Al, Cu, brass) $2,652,000 $8,287,500
Sorted plastics (PET, HDPE, PP) $2,184,000 $4,368,000
Glass cullet $140,400 $280,800
Recovered soil / aggregate $195,000 $585,000
Electricity generation $558,450 $781,830
Tipping fees $0 $3,000,000
Carbon / methane credits $50,000 $450,000
Total annual revenue $8,307,050 $21,263,130
Scenario Comparison
Metric Pessimistic Base Case Optimistic
Annual throughput 130,000 tons 195,000 tons 260,000 tons
Annual revenue $4.6M $14.2M $24.0M
Annual OPEX $5.5M $6.3M $7.5M
Net operating income ($0.9M) $7.9M $16.5M
Per-ton revenue $35 $73 $92
Per-ton net margin ($7) $40 $63
Simple payback Never (loss) 5.4 years 2.6 years

CAPEX: $42,500,000 (range $40M–$45M). Discounted payback (10% rate): ~9.2 years. 15-year NPV: ~$17.6M. Project IRR (base case, 15-year horizon): ~14%.

Autonomous Operations Architecture

Target: 90%+ autonomous operation with a staff of 14 people running a 1,000 TPD facility (versus 45–60 at a conventional MRF). Annual labour cost: $910,000 (14 staff × $65,000 average fully loaded).

System Technology Key Specifications

Primary optical sort TOMRA AUTOSORT (3 units in series) NIR spectrometer at 320 scan lines/second + VIS camera, 2,000 mm belt at 3 m/s, 256 pneumatic nozzles at 6 bar, 95%+ detection accuracy, 90–95% ejection purity

Robotic QC AMP Robotics Cortex (2 units) AI vision, delta-robot arm at 80 picks/minute, self-learning accuracy improvement, 5 kW per unit

Master PLC Allen-Bradley ControlLogix 5580 EtherNet/IP backbone, 8 remote I/O racks (AB 1756‑EN4TR)

SCADA Ignition by Inductive Automation Redundant Dell PowerEdge R750 servers, web dashboards, mobile push-notification alarms, 10+ year historian, multi-site support

HMI panels AB PanelView 5510 (22′′) 4 units at local stations

Network Cisco IE‑4010 industrial switches (6 units) 1 Gbps EtherNet/IP, OPC-UA for SCADA-to-PLC, VPN remote access

UPS Eaton 9PX 6 kVA (2 units) Control-system backup power

Phase 2 roadmap: autonomous wheel loader (Volvo LX04 / CAT autonomous), AGV bin transport, predictive maintenance via ML on vibration/temperature data, dynamic sort recipes driven by real-time commodity pricing, autonomous excavation (Built Robotics).

Water Balance & Treatment
Use Flow (GPM) Daily Volume (gal)
Sink-float tank makeup 25 30,000
Dust suppression (fog nozzles, 12 transfer points) 15 18,000
Thermal-unit quench tank 30 36,000
Cooling-tower makeup 150 180,000
Boiler feedwater makeup (demineralised, 10 12,000
Emissions control (spray-dryer lime slurry) 20 24,000
Floor washing / general 10 12,000
Total process water 260 312,000

Recycling rate: 57.7% (180,000 GPD closed-loop). Net fresh-water consumption: 132,000 GPD. On-site treatment: 20 ft diameter clarifier, sand filter, pH adjustment, RO system (Dow FilmTec BW30, 5 GPM for boiler makeup). Zero process-water discharge to surface water — all to POTW or recycled.

Noise Analysis
Criterion Limit Predicted Status
Daytime (7 AM–10 PM) residential 55–65 dBA 48 dBA continuous, 61 dBA with loader Compliant

Nighttime (10 PM–7 AM) residential 45–55 dBA 48 dBA continuous Marginal — loader operations restricted at night

OSHA workplace 8‑hr TWA 90 dBA 85–95 dBA by area Hearing protection required in shredder/air-classifier zones

Building-shell TL: 25 dB (R‑19 insulated metal panels). Distance attenuation to 200 ft setback: 36.5 dB. Combined continuous boundary noise: 47.6 dBA. Mitigation: acoustic enclosures on shredder (15–20 dB reduction), inlet/outlet silencers on air-classifier blower, 8 ft barrier wall on cooling tower, earthen berm along residential boundaries (5–8 dB insertion loss).

SCADA / Control-System Simulator (Python)
Attribute Detail
File software/control_system.py
Language Python 3.8+ (standard library only — no external dependencies)
Lines of code 847

Classes FacilityController, ProcessingStage (base), ReceivingTipping, PreSort, MechanicalSeparation, OpticalSorting, MaterialProcessing, ThermalProcessing, ResidualsManagement

Data classes Alarm, Sensor, MaterialStream (with total property and scale() method)

Enumerations StageStatus (RUNNING, STOPPED, FAULT, MAINTENANCE), AlarmSeverity (INFO, WARNING, CRITICAL)

Simulation features 7-stage sequential material-flow processing, per-component energy balance, sensor simulation with noise, stochastic fault injection (0.2% per timestep), alarm management with severity grading, auto-restart attempts, CSV data logging, text-based SCADA dashboard

Thermal model First-law energy balance: Q in = ṁ × LHV, boiler efficiency 82%, Rankine-cycle 29.6%, combined generator efficiency 94%, parasitic-load subtraction

Feed composition model Plastics 18%, paper 22%, ferrous 5%, non-ferrous 2%, glass 5%, organics 15%, textiles 8%, wood 6%, residuals 19% — ±10% variability per timestep

Outputs facility_log.csv with per-minute rows: timestamp, elapsed hours, feed rate, cumulative input, per-stage status/input/output/power/runtime, gross and net generation, total consumption, total recovered, total to landfill, active alarms

Usage python control_system.py [--duration HOURS] [--timestep SECONDS]
Design Codes & Standards Referenced

ASCE 7‑22 (loads), ACI 318‑19 (concrete), AISC 360‑22 (steel), NFPA 13 (sprinklers), NFPA 652 (combustible dust), NFPA 850 (generating plants), 40 CFR Part 60 Subpart Eb (large MWC), 40 CFR Part 62 Subpart FFF (federal plan), 40 CFR Part 403 (pretreatment), 29 CFR 1910.95 (noise), ASHRAE 62.1 (ventilation), CMAA Specification No. 70 (cranes), ASTM D1586 (SPT), ASTM D2850 (triaxial), ASTM E1155 (floor flatness), ISO 10816 (vibration), ISO 9613 (outdoor sound), EPA Methods 1–5, 23, 26A, 29 (stack testing), AASHTO HS‑25 (pavement loading), IBC, IFC, NEC/NFPA 70, IMC, IPC, ADA.

What Is in the Package
Path Description
README.md Project overview, facility specs, revenue model, package contents

specs/TECHNICAL_SPECIFICATIONS.md Full engineering specifications: site requirements, processing-hall dimensions, 7-stage equipment specs with throughput and power calculations, mass balance (all 7 stages traced), energy balance, water balance (312,000 GPD process, 57.7% recycle rate), emissions and air quality (full MACT compliance table), noise analysis with logarithmic-addition boundary predictions

blueprints/FACILITY_DESIGN.md Building layout, site plan, 5-zone interior arrangement, utilities (electrical, water, gas, compressed air, fire protection), truck-traffic flow with WB‑67 design vehicle, environmental controls (negative-pressure ventilation, HEPA filtration, tipping-floor misting, enclosed conveyors, noise barriers, biofilter odour control)

blueprints/PROCESSING_STAGES.md All 7 stages documented individually: function, input parameters, equipment specs with named models, output streams, throughput rates, power consumption by component, staffing per shift, maintenance intervals per component, failure-mode analysis per stage with cause/effect/mitigation

blueprints/EQUIPMENT_BOM.md 80+ line-item bill of materials across 12 categories, each with manufacturer, model, quantity, unit cost, total cost, lead time (4–52 weeks), key specifications, and maintenance interval. Equipment subtotal $36,842,400; total installed $49,737,200

blueprints/ENERGY_RECOVERY.md Thermal-unit design (moving-grate combustion, 3-zone, 850–1,100 °C), waste-composition heating-value table, LHV moisture-correction formula, HRSG specs (3-pass water-tube, 1,200 m²), steam-turbine Rankine-cycle calculation, parasitic-load breakdown, net-export calculation, annual electricity production, APCD train specs (baghouse, ACI, SCR, SDA), full MACT compliance table with margins, ash-management plan with metals recovery from bottom ash, Sankey energy-flow diagram, first-law check, Carnot comparison

blueprints/AUTONOMOUS_OPERATIONS.md Autonomous staffing model (14 people vs. 45–60 conventional), per-stage automation architecture with named sensors and control logic, central SCADA hardware list (Allen-Bradley ControlLogix 5580, Ignition SCADA, Cisco IE‑4010 switches), network architecture diagram, control philosophy (start/stop sequence, fault handling, auto-recovery), remote-monitoring capability, autonomy metrics, Phase 2 upgrade roadmap

financials/BUSINESS_PLAN.md Full financial model: CAPEX breakdown ($42.5M across 6 categories), OPEX ($6.3M/year with per-category detail), 8 revenue streams with pricing references to ISRI, LME, RecyclingMarkets.net, 3-scenario sensitivity analysis (pessimistic/base/optimistic), discounted payback at 10%, NPV, IRR, 8 risk factors rated and mitigated, 45-person staffing plan with per-role wages

financials/REGULATORY_PATHWAY.md 11-section compliance guide: federal permits (RCRA, CAA Title V, CWA NPDES, NEPA), state permits (solid waste, air, water, utility interconnection), local permits (zoning/CUP, building, fire marshal), environmental-impact assessment scope and process, public-hearing requirements, OSHA standards (14 specific standards, 10 safety programs), 24-month master permitting schedule with Gantt chart, ongoing compliance requirements (annual reporting, inspections, CEMS), permitting-cost breakdown, regulatory-risk matrix

software/control_system.py 847-line Python 3.8+ SCADA simulator: 7-stage material-flow model, energy-balance calculation, alarm management, CSV logging, text-based dashboard — standard library only, no dependencies

software/facility_log.csv Sample output from control-system simulator — per-minute rows with 39 columns of operational data

25-landfill-recycle-center-hero.svg Hero illustration (SVG vector)
LICENSE Proprietary licence — no licence granted without written permission
MANIFEST.json Machine-readable package metadata (13 core files, maturity level 1)
CHANGELOG.md Change log per Keep a Changelog convention
CITATION.cff Citation metadata (CFF 1.2.0)
CONTACT_INFO.txt Inventor contact details
How this is delivered

This package ships on a single Blu-ray disc, posted to the delivery address on your order. The archive on the disc is AES-256 encrypted; the passphrase is sent separately, by email, once the disc is despatched — so the disc alone is of no use to anyone who intercepts it.

Discs are despatched by tracked, signed-for post. Allow 5 business days for mastering and verification before despatch.

© 2026 Christopher Gabriel Brown. All rights reserved.

Photo

Truck-mounted mobile sorting plant on an open landfill with gulls

Footnotes

  1. Product number 8473.
  2. Family: environment.
  3. Purchase: When you buy, you buy the use of that blueprint only.
Write Your Own Review
You're reviewing:25-landfill-recycle-center
© 2026 Christopher Gabriel Brown (CRI-ONE), cri-one.com